General description of the project:
The length of line 6 of Tehran metro is about 38 km.
The passing of the subway by the residential houses caused vibration and noise in some areas adjacent to this line, which was designed and produced by designing and simulating noise and vibration pads for these areas.
Iteda measured the vibration level after seismography, and after installing the vibration absorbing pads, the performance was validated.
Finally, the performance of these pads was approved by various elements of the project and it was able to attract people’s satisfaction at a higher level.

Scope of work:

  • Design and simulation of vibrations and noise
  • Design and production of vibration absorbing pads
  • Seismography and recording of vibrations before and after installing vibration absorbing pads

Employer:

Chilco, Sabir International, Ahab companies